500 Fifth Avenue North: Project Schedule

 
Our new campus will be developed in phases over 15 years. The first phase began in summer 2008, after the Seattle Center 5th Ave N Parking Garage was completed. The new campus is expected to open in late 2010.

Fall 2005

  • Master Use Permit (MUP) process for garage
  • Queen Anne/Magnolia Design Review Board meeting #1
  • Garage design process (through winter 2007)
  • Master Plan and Phase 1 design process for campus (through fall 2008)

Winter 2006

  • Application filed for campus Major Phased Development
  • Queen Anne/Magnolia Design Review Board meeting #2
  • Permitting process for campus Major Phased Development (through fall 2006)
  • Tree preservation work on Fifth Avenue North

Spring 2006

  • Campus draft EIS issued by city of Seattle
  • Draft EIS comment meeting

Summer 2006

  • Queen Anne/Magnolia Design Review Board meeting #3
  • Power line relocation (through fall 2006)
  • Building permit process for parking garage (through summer 2007)

Fall 2006

  • Final EIS
  • Final Queen Anne/Magnolia Design Review Board meeting
  • Property ownership transferred
  • Master Use Permit process for campus Phase 1 (through spring 2007)

Winter 2007

  • Seattle Center 5th Ave N Parking Garage groundbreaking
  • Parking garage construction (through mid-2008)

Summer 2008

  • Parking garage completion

  • Campus construction Phase 1 (through late 2010)

Spring 2011

  • Foundation moves into campus
Questions or comments about the project may be emailed to 500Fifth@gatesfoundation.org.
 
 
  • Bookmark & Share:
  • Digg
  • Delicious
  • Facebook
  • Newsvine
  • Reddit
  • StumbleUpon
  • Twitter
  • Email